SIT Non-Functional Test and Test Data Approaches & Plans 


SIT Non-Functional Test Approach & Plan 

The SIT Non-Functional Test Approach & Plan describes the associated objectives, scope, approach, schedule, management, governance, and assurance of the SIT Non-Functional Stage. 

On Thursday 11 April, the Programme published the SIT Non-Functional Test Approach & Plan for a five working day assurance review. The assurance review window closes at 17:00 on Wednesday 17 April 2024.

This document was previously issued for industry consultation and feedback, and this consultation window closed on Thursday 2 April 2024

SIT Non-Functional Test Approach & Plan v0.5 (clean)

SIT Non-Functional Test Approach & Plan v0.5 (red-lined)

SIT Non-Functional Test Approach & Plan Consolidated Comments Log

To provide your feedback, please download the SIT Non-Functional Test Approach & Plan Assurance Review Comments Log spreadsheet below. As this is an assurance review, the Programme kindly requests that you please limit your feedback to the red-lined areas of the document. Once you have filled out the spreadsheet, please save with your organisation’s short name, and email it to [email protected]

SIT Non-Functional Test Approach & Plan Assurance Review Comments Log

Once the assurance review period closes on Wednesday 17 April, the Testing Team will review any feedback and make changes if required. Following this, the Programme will present the document at the Extraordinary Non-Functional Test Working Group (NFTWG) on Tuesday 30 April before taking it to the Systems Integration Testing Advisory Group (SITAG) on Wednesday 15 May for approval. 

If you have any questions, please email the Testing Team at [email protected]

testing.jpg

online2.jpg

SIT Non-Functional Test Data Approach & Plan

The SIT Non-Functional Test Data Approach & Plan aims to define a Test Data Approach specifically for the SIT Non-Functional Tests. It seeks to provide a detailed view of specific data required per participant role.   

SIT Non-Functional Test Data Approach & Plan (clean)

On 26 March 2024, the Programme published the SIT Non-Functional Test Data Approach & Plan for consultation. This consultation closed on Friday 5 April 2024. Thank you to all participants who provided feedback and input on this document.

The Testing team will review the feedback and make any required changes to the document. The feedback and the Programme’s responses will be published in a Consolidated Comments Log.

You can review the Consolidated Comments Log along with a red-lined version of the document below, as part of a five working day assurance review period. The assurance review opened on Thursday 11 April and closes at 17:00 on Wednesday 17 April

SIT Non-Functional Test Data Approach & Plan (red-lined)

SIT Non-Functional Test Data Approach & Plan Consolidated Comments Log

To submit your assurance review feedback, please download the SIT Non-Functional Test Data Approach & Plan Assurance Review Comments Log below and once complete, email it to [email protected] by 17:00 on Wednesday 17 April 2024.

SIT Non-Functional Test Data Approach & Plan Assurance Review Comments Log

Once this assurance review is complete, the document will be presented to the Data Working Group (DWG), before going to the Systems Integration Testing Advisory Group (SITAG) on 15 May 2024 for sign-off.

If you have any questions, please email the Testing Team at [email protected]