SIT Functional Test Scenarios and Test Cases Cycle 1
SIT Functional Test Scenarios & Test Cases: Cycle 1
The Programme has updated the Systems Integration Testing (SIT) Functional Test Scenarios and Test Cases for Cycle 1.
- Themes 1-5 were approved at the Testing and Migration Advisory Group (TMAG) meeting on Wednesday 20 December 2023.
- Themes 6, 7 and 9 were approved at TMAG on Wednesday 17 January 2024.
- Theme 8 was approved at the Systems Integration Testing Advisory Group (SITAG) meeting (formerly TMAG) on Wednesday 21 February 2024.
Subsequent updates to the baselined artefacts have been issued as part of our maintenance.
You can view the Release Notes for SIT Functional Test Scenarios and Cases below. The Release Notes provide a complete inventory of files that form the current baseline, as well as candidate files for additions to the baseline which are subject to industry approval.
If you have any questions, please email the Testing team at [email protected]
SIT Functional Cycle 1 Release Notes
Short Name | Doc Number | Theme | Version |
---|---|---|---|
MHHS System Integration Test Scenarios and Cases 26 Feb Release Note | MHHS-DEL2343 | SIT F Cycle 1 Release Notes | 1.0 |
MHHS System Integration Test Scenarios and Cases 17 Jan Release Note | MHHS-DEL2170 | SIT F Cycle 1 Release Notes | 1.0 |
MHHS System Integration Test Scenarios and Cases 3 Apr Release Note | MHHS-DEL2481 | SIT F Cycle 1 Release Notes | 1.1 |
MHHS System Integration Test Scenarios and Cases 01 Mar Release Note v1.1. | MHHS-DEL2343 | SIT F Cycle 1 Release Notes | 1.1 |
MHHS System Integration Test Scenarios and Cases 2 February Release Note | MHHS-DEL2189 | SIT F Cycle 1 Release Notes | 1.0 |
MHHS System Integration Test Scenarios and Cases 19 Jan Release Note | MHHS-DEL2177 | SIT F Cycle 1 Release Notes | 1.0 |
MHHS System Integration Test Scenarios and Cases 12 Jan Release Note | MHHS-DEL2156 | SIT F Cycle 1 Release Notes | 1.0 |
Where can I find the individual Test Scenarios and Test Cases for Cycle 1?
You can view information and artefacts relating to the individual themes on the following pages of this website:
- SIT Functional Cycle 1 Theme 1: New Connections
- SIT Functional Cycle 1 Theme 2: Change of Registrations
- SIT Functional Cycle 1 Theme 3: Change of Supplier
- SIT Functional Cycle 1 Theme 4: Change of Data Service
- SIT Functional Cycle 1 Theme 5: Change of Metering Service
- SIT Functional Cycle 1 Theme 6: Metering Changes
- SIT Functional Cycle 1 Theme 7: Consumption
- SIT Functional Cycle 1 Theme 8: Settlements
- SIT Functional Cycle 1 Theme 9: Industry Standing Data (ISD)
If you have any questions, please email the Testing team at [email protected]