Previous Migration Sprint
Migration Sprint 3
Sprint 3 execution started on Wednesday 3 June 2026 and ran until Tuesday 4 August 2026.
Sprint Planning
Sprint 3 Planning opened on Wednesday 13 May 2026 and the Sprint 3 Baselined Schedule is available on Kestrel.
All Suppliers were required to submit their weekly granularity forecast plans by Wednesday 20 May 2026.
For dates on the next planning window, please see the Migration Sprints page of this website.
Sprint Execution
Sprint 3 execution started on Wednesday 3 June 2026 and closed on Tuesday 4 August 2026.
The Migration Control Centre (MCC) actively monitored migrations during Sprint execution.
Information on migration processes was shared via Programme governance.
Sprint Retrospective
There is a Sprint 3 retrospective on 17 August 2026 to reflect on the closed Sprint, celebrate successes, capture lessons learned, and agree improvements for future cycles.
If there are any lessons learned that you would like to be considered for this session, please email the Migration team at [email protected]
Key Timelines
- Wednesday 20 May 2026 - Submission deadline:
Deadline for all Suppliers to have submitted their schedules (by the end of the day) - Wednesday 27 May 2026 - Sprint 3 baseline published:
- Baselined - Committed and forecast schedule released to Suppliers
- Baselined - Aggregate schedules released
- Wednesday 3 June 2026 - Sprint 3 Execution started:
- Supplier Migrations began, following Baselined committed schedule
- Tuesday 4 August 2026 – Sprint 3 Execution ended
Need support from MCC?
If you have any questions about Migration, please fill out the MCC Request and Enquiry Form below, and the team will get back to you as soon as possible. Thank you.