Change Request CR009 approved by Ofgem

◆ Published: 01/09/2022

On 26 August 2022, Ofgem approved CR009: M3 and M5 milestone date changes, and published its formal decision here.

Aligning with the Programme's Change Control Process, the MHHS Programme Management Office (PMO) is actioning Ofgem’s decision and next steps. This includes:

  • Updating the Programme Interim Plan on a Page (POAP) with the revised milestone dates
  • Communicating the decision to Programme Participants

The proposed revisions to the Interim POAP were presented to the Programme Steering Group (PSG) on 10 August 2022, alongside discussion on CR009. The new version of the Interim POAP, following approval of CR009, is available on the Planning page of this website.
 
If you have any questions, please email [email protected]